At the 96th Street beach entrance on a Saturday morning, the farmers market tents go up on the Surfside side. Behind them, a new path heads south between post-and-rope fencing toward 87th Terrace. At each street end along the way, a low, triangular mound of sand planted with sea oats sits between the dune line and the gap people walk through to the water.
Those mounds were part of the plan. The Town of Surfside's 2026 Dune Restoration and Beautification project raised and replanted the dunes between 87th Street and 96th Street. It also paid particular attention to the spots where the dune line is broken on purpose, the beach access points. They're where residents cross onto the sand, where the Town holds its beach events, and where most of this year's visible changes are.
Built From the North End Down
The Town announced the work in a May 2026 construction notice. Construction started Monday, May 11, 2026. The notice called for "restoration and elevation of existing dunes," native dune vegetation, and "maintenance and enhancement of the existing pedestrian beach walking path." It projected completion by Sept. 8, 2026.
The Town Manager's reports over the summer show the path was built from 96th Street south. Dickerson Construction was the contractor, and Kimley-Horn was the design firm and engineer of record.
Town Manager report | Where the work stood |
|---|---|
Aug. 11, 2026 | Walking path complete from 96th Street to 93rd Street, built with "Surfside mix" |
Sept. 3, 2026 | Path complete from 96th Street to 87th Terrace. Post-and-rope fencing going in from 96th Street south. Diverter dunes installed at each beach access point. Work 75% complete |
Oct. 13, 2026 | Dickerson "has completed the project." Work listed as 100% complete, with Kimley-Horn doing final quality checks and punch-list items on the October schedule |
The October 13 report gives a substantial completion date of Sept. 1, 2026. That was a week ahead of the date the May notice projected.
According to the May notice, the work started at the beach access crossing and ran through the dune section already built between 90th Street and 92nd Street, "in accordance with guidance from the Florida Department of Environmental Protection." A May 2025 Town update said the earlier work around 92nd Street and south of 90th Street was done at no cost to the Town, because a nearby private development was required to do it. So the 2026 contract finished a stretch of dune the town had been rebuilding piece by piece.
Why Every Access Point Got a Mound
A dune works as a wall only where it's continuous, and every street end in Surfside is a deliberate gap in it. The diverter dunes are meant for those gaps. The November 2026 Surfside Gazette describes them as "independent, low, triangular-shaped sand mounds planted with sea oats." It says they are designed "to reduce the energy of storm surge while also allowing seawater to recede, helping to limit the movement of water and sand inland during significant storm events."
Surfside used this idea before most of Florida did. A January 9, 2018 Town Commission packet records that the Town had installed Florida's first two diverter dunes "at street access points." The November Gazette says the 2026 project added more of them to supplement those originals, which it also calls the first such features in the state.
Two mounds at a couple of street ends have grown into a mound at every crossing. By Sept. 3, the Town Manager's report said the diverter dunes were in "at each beach access point." For anyone who crosses at the same street end every morning, that's the most noticeable change on the beach.
What Was Planted Along the Rope Line
The September report also listed landscaping on both the east and west sides of the walking path, beach-access mats, and reinstalling the signage that was removed during construction. The Town's 2025 bid addendum for the project called for these native species:
- Sea oats
- Sea grape
- Red-tip cocoplum
- Bush seaside tansy
- Saltmeadow cordgrass
- Golden creeper
- Dune sunflower
- Seaside elder
- Beach morning glory
The Gazette explains why that list matters: native dune vegetation helps "stabilize sand and reduce erosion." The May notice adds that healthy dunes provide habitat for native wildlife, including protected sea turtles. New plantings take time to fill in, so the rope line along the path will look different by spring than it does in November.
On the bay side, the Town's attention to native plants also reached Flamingo Garden at 92nd Street and Bay Drive. The November Gazette reports that Vice Mayor Dayana Benmergui and Acting Town Manager Sandra McCready visited the garden with Ivy Hernandez of Green Spirit Miami to learn about native plants. That makes a good inland stop if you want to see some of the same plant types up close.
The Contract, and Who Else Is Paying In
The Dickerson contract is listed at $2,549,630.60. As of the Oct. 13 report, the Town had paid $1,967,200.00, or 77%, leaving a balance of $582,430.60 while the final checks were done. In the Sept. 3 report, payments stood at 67% with the work 75% done.
Part of the cost will come from beachfront development. The November Gazette reports that the Town Commission modified the prior development order for Ocean House at 9309–9317 Collins Avenue so that the project must contribute toward the Town's dune restoration work. The stated aim is "helping offset costs that would otherwise fall on residents while strengthening coastal protection." It's the same approach the Town used for the earlier section between 90th and 92nd Streets.
This Winter's Beach Calendar Is Set at the Street Ends
The Town's beach events are at the same street ends the project rebuilt. Here's the corridor from north to south:
- 96th Street beach entrance. The 96th St. Surfside Farmers Market is open every Saturday and Sunday from 9:30 a.m. to 3:30 p.m. on the Surfside side of the entrance. It's sponsored by the Tourist Board, and the 2026–2027 season runs from Oct. 4, 2026 through May 30, 2027, with "fresh items, specialty foods, artisanal goods and more." This is also where the new path starts.
- 96th Street Park. Parks and Recreation's Winter Wonderland is scheduled for Sunday, Dec. 13, 2026 at 10 a.m. Family Fun Day is set for Jan. 31, 2027 at 1 p.m. at the same park.
- 93rd Street Beach. The Tourist Board's Music on the Beach series brought a classic rock concert here on Sunday, Nov. 15. Guests brought their own beach chairs, and seating was first come, first served. In August, 93rd Street was also where the first finished section of path ended.
- Between 92nd and 90th Streets. This is the dune section rebuilt earlier, which the 2026 work linked into the rest of the corridor.
- 87th Terrace. The path's southern end, completed by the Sept. 3 report. Veterans Park, at 8750 Collins Avenue, is just to the south and held the Town's Veterans Day Ceremony on Nov. 11.
Walking the whole route covers the nine blocks between the two ends of the project. On a weekend morning, it can start with fresh items and specialty foods at the market and end at the southern rope line. In her November message, Acting Town Manager Sandra McCready encouraged residents to "take advantage of oceanside activities" as the weather cools, starting with the weekend market at 96th Street. Town Hall will be closed for Thanksgiving on Nov. 26. The farmers market's posted season covers every weekend from now through May.
Surfside's beachfront condos face this rebuilt dune line. If you're thinking about what your oceanfront or near-beach property is worth this season, Rafael Szydlowski can put together a clear, data-backed picture of where you stand. Request a Free Home Valuation and we'll start with your street end.